Saturday, May 22, 2010
Slab's done!
The day after the pods, slab was poured. Going pretty well so far.
Just something to christen our house.
As you can see in the background, the fence is finished.
Pods!
Foam Pods and grills laid out in preparation for slab.
Monday, May 17, 2010
Did someone say "Pipes"?!
Last Thursday the cement for the piering was getting finished. Today (Monday), I rock up after work and Boo Yaa!!! We got pipes.
Pour that Cement!
The past week or two have gone so quickly. As soon as we got the retaining wall erected, there's been significant movement on our lot almost everyday.
The House has an outline now.
We can imagine our house now. It's finally not just an empty lot.
I wonder what's over there!!!
Thursday, May 13, 2010
Yeh Boy!!!!! The house has officially started.
Visited the block today and Boo Yaa!!! Piering!!!
Retaining Wall Finished!
Tuesday, May 11, 2010
Retaining wall started
Retaining wall has started today. Cement slab has been laid and is awaiting the stacks blocks to be laid tomorrow
Monday, May 10, 2010
Excavation complete!
The excavation is complete and we are jumping with joy
Retaining wall blocks
Since we need to install a retaining wall on the left hand side of our block, we went retaining wall block shopping on Saturday. We chose Wallstone Eco Block.
Wisdom sign and port-a-loo
Construction is about to start! We now have a Wisdom sign and
port-a-loo for the workers
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Building Timeline
- 22/11/10
-Get keys
- 18/11/10
-Concrete done
- 15/11/10
-Walk through
- 11/11/10
-Driveway started
- 04/11/10
-Carpet laid
- 03/11/10
-Splashback installed
- 28/10/10
-Render finished
- 23/10/10
-Tiles finished
- 22/10/10
-Tiles started
- 21/10/10
-Media unit in
- 21/10/10
-Alarm installed
- 21/10/10
-lights installed
- 15/10/10
-Showers installed
- 15/10/10
-Toilets installed
- 15/10/10
-Bathtub installed
- 14/10/10
-Interior painted
- 14/10/10
-Back door lacquered
- 14/10/10
-Front door lacquered
- 11/10/10
-Garage doors installed
- 01/10/10
-Porch tiles done
- 01/10/10
-Wet area tiles done
- 30/09/10
-Rendering Colour
- 28/09/10
-Kitchen cup. installed
- 28/09/10
-Vanities installed
- 27/09/10
-Kitchen cup. delivered
- 27/09/10
-Theatre unit delivered
- 27/09/10
-Vanities delivered
- 21/09/10
-Waterproofed wet areas
- 20/09/10
-Down pipes installed
- 17/09/10
-Doors went in
- 14/09/10
-Rendering started
- 13/09/10
-Internal lining started
- 09/09/10
-Batts are in
- 08/09/10
-Eaves finished
- 07/09/10
-Eaves started
- 31/08/10
-Bricks cleaned
- 30/08/10
-Wiring done
- 27/08/10
-Bricks finished
- 17/08/10
-Brickwork started
- 16/08/10
-Bricks arranged
- 04/08/10
-Cement delivered
- 12/07/10
-Bricks delivered
- 29/06/10
-Roof tiles finished
- 25/06/10
-Roof tiles started
- 24/06/10
-Roof tiles delivered
- 24/06/10
-Guttering complete
- 16/06/10
-Frame completed
- 15/06/10
-Frame started
- 12/06/10
-Site fenced
- 11/06/10
-Frame arrived
- 04/06/10
-Windows arrived
- 21/05/10
-Fence finished
- 21/05/10
-Slab poured & finished
- 20/05/10
-Foam pods laid
- 17/05/10
-Piping laid out
- 13/05/10
-Piering started
- 13/05/10
-Retaining wall finished
- 11/05/10
-Retaining wall started
- 10/05/10
-Lot excavated
- 08/05/10
-Chose ret. wall blocks
- 05/05/10
-Port-a-loo arrived
- 03/05/10
-Wisdom sign posted
- 25/03/10
-Council approval
- 01/03/10
-Lodged to co
uncil
- 24/02/10
-Developer approval
- 19/02/10
-Re-submit to developer
- 09/02/10
-Made edits to plans
- 08/02/10
-Rejected by developer
- 29/01/10
-Plans to developer
- 23/01/10
-Colour appointment
- 19/12/09
-Signed contract
- 12/12/09
-Changes to plans
- 09/12/09
-Received updated
plan
- 21/11/09
-Changes to plans
- 21/11/09
-Signed final tender
- 18/11/09
-Received 3rd tender
- 14/11/09
-Changes to 2nd tender
- 11/11/09
-Received 2nd tender
- 24/10/09
-Changes to 1st tender
- 23/10/09
-Received 1st tender
- 03/10/09
-Started tender process
- 6/11/09
-Land contract exchanged
- 02/9/09
-Deposit placed on land
Our Rouse
Our Rouse
Wisdom Homes
The New Rouse Hill
Followers
Blog Archive
▼
2010
(56)
►
November
(5)
►
October
(21)
►
September
(6)
►
August
(7)
►
June
(2)
▼
May
(12)
Slab's done!
Pods!
Did someone say "Pipes"?!
Pour that Cement!
The House has an outline now.
I wonder what's over there!!!
Yeh Boy!!!!! The house has officially started.
Retaining Wall Finished!
Retaining wall started
Excavation complete!
Retaining wall blocks
Wisdom sign and port-a-loo
►