Building Timeline
- 22/11/10
-Get keys
- 18/11/10
-Concrete done
- 15/11/10
-Walk through
- 11/11/10
-Driveway started
- 04/11/10
-Carpet laid
- 03/11/10
-Splashback installed
- 28/10/10
-Render finished
- 23/10/10
-Tiles finished
- 22/10/10
-Tiles started
- 21/10/10
-Media unit in
- 21/10/10
-Alarm installed
- 21/10/10
-lights installed
- 15/10/10
-Showers installed
- 15/10/10
-Toilets installed
- 15/10/10
-Bathtub installed
- 14/10/10
-Interior painted
- 14/10/10
-Back door lacquered
- 14/10/10
-Front door lacquered
- 11/10/10
-Garage doors installed
- 01/10/10
-Porch tiles done
- 01/10/10
-Wet area tiles done
- 30/09/10
-Rendering Colour
- 28/09/10
-Kitchen cup. installed
- 28/09/10
-Vanities installed
- 27/09/10
-Kitchen cup. delivered
- 27/09/10
-Theatre unit delivered
- 27/09/10
-Vanities delivered
- 21/09/10
-Waterproofed wet areas
- 20/09/10
-Down pipes installed
- 17/09/10
-Doors went in
- 14/09/10
-Rendering started
- 13/09/10
-Internal lining started
- 09/09/10
-Batts are in
- 08/09/10
-Eaves finished
- 07/09/10
-Eaves started
- 31/08/10
-Bricks cleaned
- 30/08/10
-Wiring done
- 27/08/10
-Bricks finished
- 17/08/10
-Brickwork started
- 16/08/10
-Bricks arranged
- 04/08/10
-Cement delivered
- 12/07/10
-Bricks delivered
- 29/06/10
-Roof tiles finished
- 25/06/10
-Roof tiles started
- 24/06/10
-Roof tiles delivered
- 24/06/10
-Guttering complete
- 16/06/10
-Frame completed
- 15/06/10
-Frame started
- 12/06/10
-Site fenced
- 11/06/10
-Frame arrived
- 04/06/10
-Windows arrived
- 21/05/10
-Fence finished
- 21/05/10
-Slab poured & finished
- 20/05/10
-Foam pods laid
- 17/05/10
-Piping laid out
- 13/05/10
-Piering started
- 13/05/10
-Retaining wall finished
- 11/05/10
-Retaining wall started
- 10/05/10
-Lot excavated
- 08/05/10
-Chose ret. wall blocks
- 05/05/10
-Port-a-loo arrived
- 03/05/10
-Wisdom sign posted
- 25/03/10
-Council approval
- 01/03/10
-Lodged to co
uncil
- 24/02/10
-Developer approval
- 19/02/10
-Re-submit to developer
- 09/02/10
-Made edits to plans
- 08/02/10
-Rejected by developer
- 29/01/10
-Plans to developer
- 23/01/10
-Colour appointment
- 19/12/09
-Signed contract
- 12/12/09
-Changes to plans
- 09/12/09
-Received updated
plan
- 21/11/09
-Changes to plans
- 21/11/09
-Signed final tender
- 18/11/09
-Received 3rd tender
- 14/11/09
-Changes to 2nd tender
- 11/11/09
-Received 2nd tender
- 24/10/09
-Changes to 1st tender
- 23/10/09
-Received 1st tender
- 03/10/09
-Started tender process
- 6/11/09
-Land contract exchanged
- 02/9/09
-Deposit placed on land
Our Rouse
Our Rouse
Wisdom Homes
The New Rouse Hill
Followers
Blog Archive
►
2010
(56)
►
November
(5)
►
October
(21)
►
September
(6)
►
August
(7)
►
June
(2)
►
May
(12)
►
March
(1)
►
January
(2)
▼
2009
(3)
▼
October
(3)
We have a back fence now!!! Bayden clearly loves ...
This is the entry to The New Rouse Hill. Beautiful...
First pics of our block of land
About Me
Alicia and Jose
View my complete profile
No comments:
Post a Comment